Office tenant improvements (TI) cost roughly $149 per square foot on average across the U.S., and most published guides for corporate offices land between about $108 and $375 per square foot depending on city, layout and finish level. For a small Southern Oregon business leasing its first space, the number that matters is not the national average. It is the gap between what the landlord's allowance covers and what your build-out is priced at by a licensed local contractor. We build commercial interiors in Medford and across Southern Oregon, and the cheapest way to avoid a budget shock is to get that contractor's scope in front of you before the lease is signed.
TL;DR
- A reported U.S. average for office tenant improvements is $149 per square foot, up 5.5% year over year, with high-cost metros well above it.
- National guides put a medium-quality corporate fit-out at $230 to $375 per square foot; a simple second-generation space in a smaller market usually sits well below that.
- The landlord's allowance rarely covers the whole job. The tenant pays everything above it.
- Layout, starting condition of the space, mechanical and electrical work, and IT and security drive most of the spread.
- Have a builder price the work letter and floor plan before you sign the lease, while you can still negotiate.
Table of Contents
- What tenant improvements are
- What tenant improvements cost per square foot
- What pushes the price up or down
- The tenant improvement allowance and who pays the difference
- How to get a reliable number before you sign
- Build-out versus buying and renovating
- Working with Verity Construction
- Looking ahead
- FAQ
- Sources
What tenant improvements are
A tenant improvement is any change made to a leased commercial space so it works for your business: new walls, ceilings, flooring, lighting, restrooms, a reception desk, a breakroom. The work is also called a build-out or fit-out. If you own the building yourself and are converting a space for a tenant, the same work is called a tenant improvement for the person who will occupy it.
A typical scope includes demising walls (the walls that separate your suite from the neighbor's), finishes, lighting and electrical beyond what the base building provides, heating and cooling distribution, restrooms, glass, doors and hardware, and fire protection. Design fees from an architect and engineer are often 5 to 8% of construction. Items that frequently sit outside the construction price include data cabling, furniture, specialty equipment and signage, and sometimes permit and city fees. Ask for each of these as a separate line, so none disappears from your budget.
What tenant improvements cost per square foot
Published guides are written mostly for large corporate tenants in big metros, so read them as a ceiling and a way to understand the structure of the price, not as a quote for a 1,800 square foot suite in Jackson County.
| Source and scope | Reported cost per sq ft |
|---|---|
| U.S. average office build-out, 2026 | $149 |
| Hard construction cost, lowest of 42 U.S. cities (Cincinnati) | $108.03 |
| Hard construction cost, New York City | $212.59 |
| Hard construction cost, highest of 42 cities (San Jose) | $219.32 |
| Medium-quality corporate office, regional average, Q1 2026 | $295 (range $230 to $375) |
| Baseline open layout, national average, Q1 2026 | $255 |
| High-end traditional layout, national average, Q1 2026 | $355 |
Two things stand out. First, the figures measure different things. Hard costs are construction only. The all-in figure for New York in the same Cushman & Wakefield guide reaches $330.92 per square foot once soft costs, IT, audiovisual, furniture and miscellaneous items are added. Always ask which of the two a number describes.
Second, the spread inside a single market is wide. JLL's full market ranges run from $170 to $425 per square foot depending on whether the layout is open and flexible or built around private offices and traditional finishes. JLL's authors note that the way a space is designed and specified moves cost as much as location does.
These figures are published for a specific period and refresh as new quotes come in, so treat them as a snapshot of 2026 pricing and check the guides for the latest edition.

What pushes the price up or down
Starting condition of the space
A second-generation space, one that was already an office, can be the cheapest starting point if the ceiling, lighting, restrooms and mechanical systems are in good shape and match your plan. It can also be expensive if the old layout has to be demolished and rerouted. A shell that is unfinished means pricing everything from the slab up. Ask what the landlord delivers (often called landlord's work) and what is left to you, because that line is written in the lease.
Layout and finish level
A large open floor with a few meeting rooms costs less per square foot than a plan full of private offices, glass fronts and acoustic ceilings. Every added wall brings framing, drywall, electrical, ceiling grid and often more heating and cooling zones.
Mechanical and electrical work
Finishes, heating and cooling, and electrical typically take the largest shares of an office build-out. If your plan moves walls, the ductwork and lighting move with them. Adding a server closet, a kitchen or a second restroom adds plumbing and power on top.
Technology and security
JLL reports that security, IT and audiovisual now make up about 10 to 12% of total fit-out cost, with a median 8% year-over-year increase. A small office may spend less in absolute terms, but it is worth planning conduit and power for these systems during construction rather than adding them afterward.
Materials and labor
JLL's 2026 guide points to tariffs raising the floor on material costs and to specialty trade wages running above historical averages as the workforce ages. A price from last year may be out of date, and a bid is only reliable for a limited time. Ask any contractor how long their number holds.
Permits and design
Design fees, city plan review and permit fees all sit on top of construction. Confirm with your contractor who submits the permit application and who pays the fees, so it is written down before work starts.
The tenant improvement allowance and who pays the difference
Many commercial leases include a tenant improvement allowance, which is money the landlord contributes toward your build-out, usually quoted per square foot. Typically you pay your contractor, submit paid invoices and lien waivers, and the landlord reimburses eligible costs. Read the lease for the sunset date, since an allowance not claimed by then can be lost.
The important point is that the allowance is a contribution, not a budget. The tenant pays all costs in excess of the allowance. Savills and CompStak found that allowances rose after the pandemic and peaked in late 2024, but have not kept pace with construction costs, leaving the gap between allowance and actual build-out cost wider than before.
A worked example
This is an illustration, not a quote. Say you lease a 2,000 square foot second-generation office. If the build-out lands at the reported U.S. average of $149 per square foot, the project is $298,000. If your lease offers an allowance of $60 per square foot, the landlord contributes $120,000 and you fund $178,000. Move the build-out to $100 per square foot because the space needs only a refresh, and the total is $200,000 and your share is $80,000. The same lease gives two very different outcomes, which is why the scope matters more than the allowance headline.

Who owns the improvements
As a general rule, tenant improvements typically become the landlord's property when the lease ends. That affects how long you should plan to stay: a heavy build-out on a two-year lease is hard to justify. Ownership also decides how the costs are treated on your books, so bring the lease to your accountant before construction begins.
How to get a reliable number before you sign
- Start with the lease work letter. It states what the landlord builds, what you build, the allowance, the completion date and who pays for building-standard items. Everything else is priced from it.
- Define your program. Count workstations, private offices, meeting rooms, restrooms, a kitchen or breakroom, and any specialty rooms. A rough sketch is enough to price against.
- Walk the space with a builder. An on-site visit shows the ceiling height, the condition of the mechanical systems, the electrical capacity and what the previous tenant left behind. Those details move the price more than the average per square foot does.
- Separate hard and soft costs. Ask for construction, design, permits, IT and cabling, furniture and signage as individual lines so you can compare them with the allowance.
- Add a contingency. Older buildings hide surprises behind walls. Hold a reserve against the construction total in case of unforeseen conditions.
- Match the schedule to the lease. Rent often starts on a fixed date. Confirm the construction timeline, permit timing and your move-in date together.
We do this work with owners across Southern Oregon as a licensed, bonded and insured local team, and we keep clients updated throughout the project so you see where the money is going.
Build-out versus buying and renovating
If you own property, or you are weighing a lease against owning a small building, the build-out calculation changes. With a lease, the landlord's allowance offsets some of the cost and the improvements generally stay behind. With a building you own, the full cost is yours but so is the value you create. Homeowners who run a business, or who are adding a rental or ADU alongside a commercial space, often find it useful to price both paths with the same builder.
Working with Verity Construction
Verity Construction offers commercial construction in Medford and Southern Oregon, including professional offices, tenant improvements, retail spaces and multi-family development. Pricing for commercial projects is not published, since each space and lease is different, so we price from your floor plan and work letter. You can see how we approach commercial interiors on the Professional Offices and Tenant Improvements page.

For a sense of the finished result, look at our Southern Oregon office renovation with a modern breakroom. If you are also planning work on your home, we build custom homes, whole-home remodels, additions and ADUs, and our cost guide for building a custom home in Medford shows how we lay out pricing for residential projects. When you are ready to talk about your space, start from our main site.
Looking ahead
Savills and CompStak ask whether allowances will stabilize or fall as landlords regain leverage, even while tariffs push construction costs higher. For a tenant, that points to one practical habit: negotiate the allowance and the scope of landlord's work at the same time, with a builder's number in hand. A lease signed against a verified price is a lease you can afford to build out.
FAQ
How much do office tenant improvements cost per square foot?
A reported U.S. average is $149 per square foot, while corporate fit-out guides show much higher figures in large metros and for high-end layouts. Your own cost depends on the condition of the space, the layout, and the mechanical and electrical work required. A builder's walkthrough gives a figure specific to your suite.
Who pays for tenant improvements, the landlord or the tenant?
Both, usually. The landlord contributes an allowance under the lease, and the tenant pays costs above it. Landlord's work, where the landlord builds certain items itself, is also set out in the lease.
Is the tenant improvement allowance paid up front?
Typically it is a reimbursement. You pay the contractor, submit paid invoices and lien waivers, and the landlord reimburses eligible costs, as explained by a leasing platform. Check your lease for the exact process and any deadline for claiming it.
Do I keep the improvements when the lease ends?
Usually not. Tenant improvements typically become the landlord's property at lease termination. Your lease and your accountant can confirm how the improvements are treated in your situation.
Sources
- Allwork.Space: The Bay Area Now Has The Highest Office Build-Out Costs
- Cushman & Wakefield: Office Fit Out Cost Guide 2026
- JLL: U.S. and Canada Office Fit-Out Costs Guide 2026
- Savills USA: How construction costs and TI allowances are changing
- Lorman: Landlord-Tenant Law, Tenant Improvement Allowance
- CommercialLeaseCost: Tenant Improvement Allowance Calculator
- Spacebase: Tenant Improvement Allowance Explained